Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the wp-plugin-bluehost domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/strides1/public_html/wp-includes/functions.php on line 6121

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the google-analytics-for-wordpress domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/strides1/public_html/wp-includes/functions.php on line 6121

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the archi domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/strides1/public_html/wp-includes/functions.php on line 6121

Project Details

Client:
SPDC
Project Name:
Cluster JB FYIP 5 Wells Completion Project
Location:
CLUSTER JB – FORCADOS ESTUARY OFFSHORE OIL FIELD
Year Completed:
2018
Category:
Estuary

Project Overview

VESSELS DEPLOYED:
SEWOPS: MV Tiger Shark
MV Whisky Star IV
MV Scamp
Emergency Response Vessel:    MV Thethis
Security Vessel:   MV Rhema Star
Crew Boat:   MV Joetek Azaebi

SCOPE OF WORK
• Engineering analysis and design
• Fabricate, NDT and installation of all top side piping spools
• Conversion of all actuated choke valves to manual valves.
• Replacement of dummy or missing spools topsides with actual spools as per AFC.
• Replacement of corroded and missing bolts, nuts with PTFE coated bolts and nuts.
• Complete refurbishment of the entire boat landing structures
• Carried out grit blasting and painting of the entire cluster structures.
• Flooding of the lines were done prior to diving operations
• Fabricate, NDT, and install #2 of 8” bulkline subsea risers and hookup to the existing topside piping.
• Carried out diving operations for installation of smart flanges, and sandbags.

DIVING SUPPORT: Subtech Offshore Services Nigeria Ltd
( James Fisher Subtech Group)
SMART FLANGE CONNECTORS SUPPLIER: Oceaneering/Craymond Nigeria Limited
DURATION: 3 Months

STATUS: Completed